AI wants Bitcoin miners’ power, but contracts decide who gets paid

Mining sites may offer a shortcut to electricity for AI data centers, but converting capacity takes major investment—and contract terms shape when operators collect cash.

AI wants Bitcoin miners’ power, but contracts decide who gets paid Brett Sayles

Bitcoin miners’ electricity connections are drawing interest from AI infrastructure developers, but access to power does not mean a site is ready to host computing equipment—or that its owner will quickly collect revenue. The financial outcome depends on what is being sold, who pays for construction and hardware, and what customer contracts say about fees, credits and delays.

Mining ASICs have little use for AI training, and converting a mining property can require new buildings, denser cooling, advanced networking and substantial financing. CoinShares estimated in its September mining report that AI conversion costs run roughly $8 million to $15 million per megawatt, compared with $700,000 to $1 million per megawatt for conventional mining infrastructure.

That distinction matters as SWI Group expands its AI plans after taking control of Genesis Digital Assets. SWI described Genesis sites with more than 1.3 gigawatts of energized or approved connections in June, then cited about 1.2 gigawatts of secured connections in September. It has not reconciled the figures or disclosed how much capacity can be converted economically, where GPUs will be installed, or when revenue from those sites may begin.

Different contracts, different risks

Core Scientific’s hosting model illustrates how an operator can earn fees without buying all of the customer’s computing equipment. Its second-quarter filing recorded $136.7 million in colocation revenue, and the company said 437 megawatts were generating customer bills by mid-July. The filing listed $98.8 million in license fees and $35.1 million in reimbursed electricity costs; those electricity payments carried matching expenses.

Core Scientific’s agreements with CoreWeave set an initial base license fee of $100 per kilowatt per month at most locations, with annual increases of 3.5%. But specified landlord-owned equipment can generate future fee credits of up to $1.5 million per megawatt. At the initial rate, a full credit could reduce monthly cash payments for a one-megawatt allocation from $100,000 to $50,000 while the credit is recovered.

Recognized revenue and cash receipts can also diverge under the 12-year agreement because of prepayments, construction credits and accounting rules. The contracts set delay credits in certain circumstances and allow cancellation for some delays. Core Scientific recorded $954.2 million in first-half 2026 capital expenditure, including $180.9 million funded by CoreWeave.

Power capacity is not operating capacity

A connection approval, a place in an electricity queue and power already available at a property are different stages of readiness. Texas regulators approved ERCOT’s Batch Zero review procedure in June, while the state ordered an audit of about 474 gigawatts of proposed connections for large electricity users. Neither figure alone establishes how soon a particular site can serve AI customers.

The commercial gap is visible in AI agreements more broadly: a review of contracts worth more than $100 billion found about 550 megawatts generating bills against contracted capacity exceeding 4 gigawatts. SWI Compute announced roughly $1 billion in NVIDIA system orders and initial customers on October 26, though some customer contracts remained unfinished. The company has not disclosed how much of its Genesis fundraising plans will go to specific sites.

This report draws on information from KuCoin.

Editorial checks passed Facts, figures and quotes checked against 1 source