Riot Names Anthropic in $28B Texas Lease With a 12% Rent-Credit Clause

The bitcoin miner says Anthropic will lease 910 megawatts at its Corsicana campus. If Riot cannot secure acceptable financing for tenant-installed equipment, rent credits could accrue at 12% interest.

Riot Names Anthropic in $28B Texas Lease With a 12% Rent-Credit Clause Brett Sayles

Riot Platforms has named Anthropic as the tenant behind a 15-year lease covering 910 megawatts of critical IT capacity at the bitcoin miner’s Corsicana, Texas, campus. The agreement is valued at about $28 billion, and its financing terms could require Riot to provide rent credits carrying 12% annual interest if it cannot raise money on acceptable terms.

Riot’s quarterly filing says a subsidiary signed the lease on Oct. 28 and that it became binding on Nov. 4, after board approval and review of technical specifications. The filing also identifies Anthropic as the tenant on Riot’s 191-megawatt Rockdale lease, signed in August. Anthropic therefore accounts for 1,101 megawatts of the 1,151 megawatts Riot has contracted; AMD holds the remaining 50 megawatts.

The Corsicana lease’s base rent starts at $130 per kilowatt per month and increases 3% annually. Riot estimates average annual rent of about $1.8 billion over the initial term. If Anthropic exercises both five-year extensions, Riot estimates total rent at roughly $54 billion.

How the 12% clause could work

Riot agreed to reimburse Anthropic for data center modules the tenant installs, up to $4 million per megawatt, or about $3.6 billion across the full Corsicana capacity. The reimbursement depends on Riot obtaining financing on market terms it finds reasonably acceptable.

If that financing is unavailable, Riot’s filing says it would instead give Anthropic rent credits that repay the amount, plus 12% annual interest, over the rest of the initial lease term. Riot’s stated plan is to fund reimbursements with non-recourse project debt sized to contracted rent. It estimates total project capital needs at about $5.5 billion and says it does not currently expect to issue equity for the project.

Delivery dates and Riot’s bitcoin sales

Riot plans to deliver Corsicana capacity in three phases: 400 megawatts, with the first block targeted for June 28, 2027; 200 megawatts starting Dec. 24, 2027; and 310 megawatts on July 30, 2028. If a phase is more than 270 days late, Anthropic can terminate that phase with 30 days’ notice, subject to force majeure extensions of up to 365 days. Delays beyond 60 days also trigger escalating rent credits, capped at 270 days of base rent for undelivered blocks.

Riot sold 20,264 bitcoin for about $1.5 billion during the first nine months of 2026 and held 2,418 BTC, valued at $202 million, at the end of September. The filing says Riot expects to continue selling substantially all the bitcoin it mines and does not expect significant near-term accumulation. Whether it can obtain the planned project debt—and avoid the rent-credit alternative—has not been announced.

This report draws on information from Bitcoin Magazine.

Editorial checks passed Facts, figures and quotes checked against 1 source